  1. Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.

  2. A.

     One-fourth

    B.

     One-half

    C.

     Equal to

    D.

     Twice

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is One-half the standard time.