  1. In a PERT chart

  2. A.

     All activities should be numbered

    B.

     Only important activities should be numbered

    C.

     Only critical activities are numbered

    D.

     Only selected activities are numbered

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    In a PERT chart All activities should be numbered