  1. In PERT analysis, critical path is obtained by joining events having

  2. A.

     +ve slack

    B.

     -ve slack

    C.

     Zero slack

    D.

     Dummy activities

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    In PERT analysis, critical path is obtained by joining events having Zero slack