  1. CPM has following time estimate

  2. A.

     One time estimate

    B.

     Two time estimate

    C.

     Three time estimate

    D.

     Four time estimate

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    CPM has one time estimate