  1. PERT has following time estimate

  2. A.

     One time estimate

    B.

     Two time estimate

    C.

     Three time estimate

    D.

     Four time estimate

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    PERT has three time estimate


Be The First To Comment