- Activity slack or float of any event on a PERT/CPM chart is represented by
A.
Latest start time of succeeding event earliest finish time of preceding event activity time |
B.
Latest start time of the event earliest start time of the event |
C.
Latest finish time of event earliest finish time of the event |
D.
Anyone of the above |
Answer : Option D
Explanation :
Activity slack or float of any event on a PERT/CPM chart is represented by
- Latest start time of succeeding event earliest finish time of preceding event activity time
- Latest start time of the event earliest start time of the event
- Latest finish time of event earliest finish time of the event