  1. The time which results in the least possible direct cost of an activity is known as

  2. A.

     Normal time

    B.

     Slow time

    C.

     Crash time

    D.

     Standard time

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    The time which results in the least possible direct cost of an activity is known as slow time