- When slack of an activity is negative
A.
It represents a situation where extra resources are available and the completion of project is not delayed |
B.
It represents that a programme falls behind schedule and additional resources are required to complete the project in time |
C.
The activity is critical and any delay in its performance will delay the completion of whole project |
D.
All of the above |
Answer : Option B
Explanation :
When slack of an activity is negative It represents that a programme falls behind schedule and additional resources are required to complete the project in time