Home / Mechanical Engineering / Industrial Engineering and Prod'n Mgmt :: Discussion

Discussion :: Industrial Engineering and Prod'n Mgmt

  1. If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good

  2. A.

     EF = ES + D

    B.

     LS = LFD

    C.

     LF = LS + D

    D.

     All of the above

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good
    - EF = ES + D
    - LS = LFD
    - LF = LS + D