  1. PERT analysis is based on

  2. A.

     Optimistic time

    B.

     Pessimistic time

    C.

     Most likely time

    D.

     All of the above

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    PERT Analysis. Program Evaluation and Review Technique (PERT) is a method used to examine the tasked that are in a schedule and determine a variation of the Critical Path Method (CPM).
    It analyzes the time required to complete each task and its associated dependencies to determine the minimum time to complete a project