  1. Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it

  2. A.

     Consumes time, but no resources

    B.

     Consumes resources but no time

    C.

     Consumes neither time nor resources

    D.

     Is a dangling event

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    Dummy activity on a PERT/CPM chart means, it Consumes neither time nor resources