- The assumption in PERT is
A.
A project will always be behind schedule, if left uncorrected |
B.
Cost of project will always be more than the estimated cost, if no timely corrections are taken |
C.
A project can be subdivided into a set of predictable, independent activities |
D.
Activities are fixed and can't be changed |
Answer : Option C
Explanation :
The assumption in PERT is A project can be subdivided into a set of predictable, independent activities