  1. Critical path moves along the activities having total float of

  2. A.

     Positive value

    B.

     Negative value

    C.

     Zero value

    D.

     Same value

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    Critical path moves along the activities having total float of Zero value