Discussion :: Industrial Engineering and Prod'n Mgmt
- PERT
A.
Provides an approach for keeping planning up-to-date |
B.
Provides a way for management to require that planning be done on a uniform and logical basis |
C.
Permits management to foresee quickly the impact of variations from the plan |
D.
All of the above |
Answer : Option D
Explanation :
PERT
- Provides an approach for keeping planning up-to-date
- Provides a way for management to require that planning be done on a uniform and logical basis
- Permits management to foresee quickly the impact of variations from the plan