  1. PERT is the

  2. A.

     Time oriented technique

    B.

     Event oriented technique

    C.

     Activity oriented technique

    D.

     Target oriented technique

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    PERT is the Event oriented technique