- Pick up the correct step used for scheduling a project by C.P.M.
A.
A project is divided into various activities |
B.
Required time for each activity is established |
C.
Sequence of various activities is made according to their importance |
D.
All of the above |
Answer : Option D
Explanation :
for scheduling a project by C.P.M.
-A project is divided into various activities
- Required time for each activity is established
- Sequence of various activities is made according to their importance