Home / Mechanical Engineering / Industrial Engineering and Prod'n Mgmt :: Discussion

Discussion :: Industrial Engineering and Prod'n Mgmt

  1. In crash program for a project

  2. A.

     both direct and indirect costs, increase

    B.

     indirect costs increase and direct costs decrease

    C.

     direct costs increase and indirect costs decrease

    D.

     cost is no criterion

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    In crash program for a project direct costs increase and indirect costs decrease