  1. Discrepancies of bar chart techniques are

  2. A.

     Consequential effects of lack in one activity on the finish date

    B.

     Free time available for an activity can't be predicted

    C.

     Effective monitoring/controlling can't be done

    D.

     All of the above

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    Discrepancies of bar chart techniques are
    - Consequential effects of lack in one activity on the finish date
    - Free time available for an activity can't be predicted
    - Effective monitoring/controlling can't be done