  1. PERT analysis is based upon

  2. A.

     Optimistic time

    B.

     Pessimistic time

    C.

     Most likely time

    D.

     All of these

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    PERT analysis is based upon
    Optimistic time
    Pessimistic time
    Most likely time