- Pessimistic time is
A.
The maximum time which an activity might require |
B.
The average time required for a job |
C.
The most probable time considering all conditions |
D.
The minimum time in which an activity can possibly be accomplished |
Answer : Option A
Explanation :
Pessimistic time is a concept used in the program evaluation and review technique (PERT). It represents the longest estimated time period within which a task is likely to be completed, and is used in project planning.