  1. If a worker gets a daily wage of Rs HA, then according to Rowan plan, his maximum daily earnings can be

  2. A.

     2 HA

    B.

     1.33 HA

    C.

     1.5 HA

    D.

     1.15 HA

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    If a worker gets a daily wage of Rs HA, then according to Rowan plan, his maximum daily earnings can be 2 HA