  1. In time study, the rating factor is applied to determine

  2. A.
    standard time of a job
    B.
    merit rating of the worker
    C.
    fixation of incentive rate
    D.
    normal time of a worker

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    No answer description available for this question.