When slack of an activity is negative
A.
it represents a situation where extra resources are available and the completion of project is not delayed
|
B.
it represents that a programme falls behind schedule and additional resources are required to complete the project in time
|
C.
the activity is critical and any delay in its performance will delay the completion of whole project
|
D.
all of the above
|
Answer : Option B
Explanation :
No answer description available for this question.