  1. In a network shown in the below figure, the critical path is along

  2. A.
    1-2-3-4-8-9
    B.
    1-2-3-5-6-7-8-9
    C.
    1-2-3-4-7-8-9
    D.
    1-2-5-6-7-8-9

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    No answer description available for this question.