Which of the following are the guidelines for the construction of a network diagram?
A.
Each activity is represented by one and only one arrow in the network.
|
B.
Dangling must be avoided in a network diagram.
|
C.
Dummy activity consumes no time or resource.
|
D.
all of the above
|
Answer : Option D
Explanation :
No answer description available for this question.