  1. Which of the following are the guidelines for the construction of a network diagram?

  2. A.
    Each activity is represented by one and only one arrow in the network.
    B.
    Dangling must be avoided in a network diagram.
    C.
    Dummy activity consumes no time or resource.
    D.
    all of the above

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    No answer description available for this question.