Home / Mechanical Engineering / Industrial Engineering and Production Management :: Discussion

Discussion :: Industrial Engineering and Production Management

  1. A dummy activity in a net work diagram

  2. A.
    is represented by a dotted line
    B.
    is an artificial activity
    C.
    does not consume time or resources
    D.
    all of these

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    No answer description available for this question.


Be The First To Comment