The essential condition for the decompression of an activity is that
A.
the project time should change due to decompression
|
B.
after decompression the time of an activity invariably exceeds its normal time
|
C.
an activity could be decompressed to the maximum extent of its normal time
|
D.
none of the above
|
Answer : Option C
Explanation :
No answer description available for this question.