Home / Mechanical Engineering / Industrial Engineering and Production Management :: Discussion

Discussion :: Industrial Engineering and Production Management

  1. When slack of an activity is positive

  2. A.
    it represents a situation where extra resources are available and the completion of project is not delayed
    B.
    it represents that a programme falls behind schedule and additional resources are required to complete the project in time
    C.
    the activity is critical and any delay in its performance will delay the completion of whole project
    D.
    any one of the above

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    No answer description available for this question.


Be The First To Comment