  1. Dummy activities are used to

  2. A.
    determine the critical path
    B.
    determine the project completion time
    C.
    maintain the required net work
    D.
    none of these

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    No answer description available for this question.