  1. Earliest finish time can be regarded as

  2. A.
    earliest start time + duration of activity
    B.
    earliest start time - duration of activity
    C.
    latest finish time + duration of activity
    D.
    latest finish time - duration of activity

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    No answer description available for this question.