Earliest finish time can be regarded as
A.
earliest start time + duration of activity
|
B.
earliest start time - duration of activity
|
C.
latest finish time + duration of activity
|
D.
latest finish time - duration of activity
|
Answer : Option A
Explanation :
No answer description available for this question.