Home / Mechanical Engineering / Industrial Engineering and Production Management :: Discussion

Discussion :: Industrial Engineering and Production Management

  1. Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is __________ the standard time.

  2. A.
    one-fourth
    B.
    one-half
    C.
    equal to
    D.
    twice

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    No answer description available for this question.