Home / Mechanical Engineering / Industrial Engineering and Production Management :: Discussion

Discussion :: Industrial Engineering and Production Management

  1. When slack of an activity is zero, the activity is critical and any delay in its performance will delay the completion of the whole project.

  2. A.
    Yes
    B.
    No

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    No answer description available for this question.