  1. The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as

  2. A.

     Excavation

    B.

     Surface dressing

    C.

     Cutting

    D.

     Surface excavation

    View Answer

    Workspace

    Answer : Option D