  1. The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is

  2. A.

     3250 m³

    B.

     3225 m³

    C.

     3275 m³

    D.

     3300 m³

    View Answer

    Workspace

    Answer : Option B

    Explanation :