- Pick up the correct statement from the following:
A.
If the bed level is above N.S.L. the canal is called fully in baking and the berms are designed as 3 d where d is full supply depth of water (F.S.D.) |
B.
Area of canal in cutting = BD + Sd² where B = bed width, d = depth of cutting and S is the side slope |
C.
If F.S.L. is above N.S.L the canal is called partly in cutting and partly in filling and berms are designed as 2d where d is full supply depth |
D.
All the above |
Answer : Option D
Explanation :
Explanation Not Provided