  1. Pick up the excavation where measurements are made in square meters for payment.

  2. A.

     Ordinary cuttings up to 1 m

    B.

     Surface dressing up to 15 cm depths

    C.

     Surface excavation up to 30 cm depths

    D.

     Both (B) and (C)

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    Explanation Not Provided