  1. A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved.

  2. A.

    26, 000 m3

    B.

    26, 500 m3

    C.

    27, 000 m3

    D.
    27, 500 m3

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    No answer description available for this question.