Pick up the correct statement from the following:
-
A Milestone chart
-
Completion of an activity on CPM network diagram, is generally known
-
A dummy activity
-
Military organisation is known as
-
Pick up the incorrect statement from the following:
-
Various activities of a project, are shown on bar charts by
-
Time and progress chart of a construction, is also known as
-
Critical Path Net Work helps an engineer
A.
The float may be positive, zero or negative |
B.
If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed |
C.
If the float of an activity is negative, delay in its performance is bound to delay the completion of project |
D.
If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project |
E.
All the above. |