If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
-
Works costing less than Rs. 20,000 are treated as
-
A critical ratio scheduling
-
The first method invented for planning projects, was
-
If TL is the latest allowable event occurrence time, total activity slack(s), is equal to
-
The Overall in-charge of an organisation at the site responsible for the execution of the works, is
-
Modular co-ordination of construction means proper
-
Pick up the correct statement from the following: