  1. For which of the following materials, the output of power shovels for a fixed shovel size will be maximum

  2. A.

     Moist loam

    B.

     Good common earth

    C.

     Well blasted rock

    D.

     Wet sticky clay

    View Answer

    Workspace

    Discuss Discuss in Forum


  3. The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be

  4. A.

     Rs. 8,800

    B.

     Rs. 7,600

    C.

     Rs. 6,400

    D.

     Rs. 5,000

    View Answer

    Workspace

    Discuss Discuss in Forum


  5. Crash project duration is obtained by summing the

  6. A.

     Normal durations for all the activities

    B.

     Crash durations for all activities

    C.

     Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

    D.

     Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities

    View Answer

    Workspace

    Discuss Discuss in Forum


  7. Mile Stone charts were invented in the year of

  8. A.

     1910

    B.

     1920

    C.

     1930

    D.

     1940

    View Answer

    Workspace

    Discuss Discuss in Forum


  9. Which one of the following represents an activity?

  10. A.

     Excavation for foundation

    B.

     Curing of concrete

    C.

     Setting of question paper

    D.

     All the above

    View Answer

    Workspace

    Discuss Discuss in Forum


  11. The part of a derrick crane include
    (i) Mast
    (ii) Boom
    (iii) Bull wheel
    (iv) Jack
    which of these statements are correct?

  12. A.

     (i), (ii) and (iv) are correct

    B.

     (ii), (iii) and (iv) are correct

    C.

     (i), (iii) and (iv) are correct

    D.

     (i), (ii) and (iii) are correct

    View Answer

    Workspace

    Discuss Discuss in Forum


  13. For excavating utility trenches with precise control of depth, the excavation equipment used is

  14. A.

     Hoe

    B.

     Shovel

    C.

     Dragline

    D.

     None of the above

    View Answer

    Workspace

    Discuss Discuss in Forum


  15. Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?

  16. A.

     Concrete

    B.

     Loose sand

    C.

     Asphalt

    D.

     Firm earth

    View Answer

    Workspace

    Discuss Discuss in Forum


  17. Power stations are generally treated as

  18. A.

     Light construction

    B.

     Heavy construction

    C.

     Industrial construction

    D.

     Electrical construction

    View Answer

    Workspace

    Discuss Discuss in Forum


  19. If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

  20. A.

     expected time of activity A is greater than the expected time of activity B

    B.

     expected time of activity B is greater than the expected time of activity A

    C.

     expected time of both activities A and B are same

    D.

     none of the above

    View Answer

    Workspace

    Discuss Discuss in Forum