  1. ABC analysis deals with

  2. A.

     Analysis of process chart

    B.

     Flow of material

    C.

     Ordering schedule of job

    D.

     Controlling inventory costs money

    View Answer

    Workspace

    Discuss Discuss in Forum


  3. A-B-C analysis is used in

  4. A.

     CPM

    B.

     PERT

    C.

     Inventory control

    D.

     All of these

    View Answer

    Workspace

    Discuss Discuss in Forum


  5. The interchangeability can be achieved by

  6. A.

     Standardization

    B.

     Better process planning

    C.

     Bonus plan

    D.

     Better product planning

    View Answer

    Workspace

    Discuss Discuss in Forum


  7. Earliest finish time can be regarded as

  8. A.

     Earliest start time + duration of activity

    B.

     Earliest start time duration of activity

    C.

     Latest finish time + duration of activity

    D.

     Latest finish time duration of activity

    View Answer

    Workspace

    Discuss Discuss in Forum


  9. The mathematical technique for finding the best use of limited resources in an optimum manner is known as

  10. A.

     Operation research

    B.

     Linear programming

    C.

     Network analysis

    D.

     Break-even analysis

    View Answer

    Workspace

    Discuss Discuss in Forum


  11. Standing orders which are statutory are applicable to

  12. A.

     All industries

    B.

     All process industries and thermal power plants

    C.

     Only major industries

    D.

     All industries employing more than 100 workers

    View Answer

    Workspace

    Discuss Discuss in Forum


  13. In the Halsey 50-50 plan, the following are rewarded more

  14. A.

     Past good workers

    B.

     Past poor workers

    C.

     Past average workers

    D.

     All of the above

    View Answer

    Workspace

    Discuss Discuss in Forum


  15. Gantt charts are used for

  16. A.

     Forecasting sales

    B.

     Production schedule

    C.

     Scheduling and routing

    D.

     Linear programming

    View Answer

    Workspace

    Discuss Discuss in Forum


  17. In perpetual inventory control, the material is checked as it reaches its

  18. A.

     Minimum value

    B.

     Maximum value

    C.

     Average value

    D.

     Middle value

    View Answer

    Workspace

    Discuss Discuss in Forum


  19. Service time in queuing theory is usually assumed to follow

  20. A.

     Normal distribution

    B.

     Poisson’s distribution

    C.

     Erlang distribution

    D.

     Exponential law

    View Answer