Civil Engineering :: Estimating and Costing
-
Pick up the correct statement in case of water supply.
-
In case of laying gullies, siphons, intercepting traps, the cost includes
-
In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and
-
The height of the sink of wash basin above floor level is kept
-
While preparing a detailed estimate
-
Pick up the incorrect statement regarding a master trap from the following :
-
The concrete work for the following part of the building of specified thickness is measured in square metres
-
Pick up the correct statement from the following:
-
The expected out turn of cement concrete 1 : 2 : 4 per mason per day is
-
The area of the cross-section of a road fully in banking shown in the given figure, is
A.
It is provided in between the lower end of the house drain and the street sewer |
B.
It is provided a cleaning eye at the top of the trap |
C.
The height of fresh air inlet pipe fixed vertically with wall is 3 m |
D.
The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe |
E.
The water seal is less than that of ordinary traps. |
A.
The estimated value of the work excluding the amount for contigencies, work charged establishment, tool and plants, is called work value |
B.
The actual expenditure involved to complete a work including incidental, establishment and travelling charges, is called actual cost |
C.
The formal acceptance by the administrative department for incurring an expenditure on the work, is called administrative approval |
D.
The order of a competent authority sanctioning a properly detailed estimate of the cost of a work of construction or repair is called technical sanction |
E.
All the above. |