Mechanical Engineering :: Industrial Engineering and Prod'n Mgmt
- The two bin system is concerned with
- Work study is concerned with
- Activity slack or float of any event on a PERT/CPM chart is represented by
- Acceptance sampling is widely used in
- Dummy activities are used to
- The time which results in the least possible direct cost of an activity is known as
- When slack of an activity is negative
- When slack of an activity is positive
- If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
A.
It represents a situation where extra resources are available and the completion of project is not delayed |
B.
It represents that a programme falls behind schedule and additional resources are required to complete the project in time |
C.
The activity is critical and any delay in its performance will delay the completion of whole project |
D.
All of the above |
A.
It represents a situation where extra resources are available and the completion of project is not delayed |
B.
It represents that a programme falls behind schedule and additional resources are required to complete the project in time |
C.
The activity is critical and any delay in its performance will delay the completion of whole project |
D.
Any one of the above |