- In steel plant the most important system for materials handling is
- Work study involves
- Gantt chart provides information about the
- Pick up the correct statement from the following
- Pick up the correct statement from the following
- Pick up the correct statement from the following
- Pick up the incorrect statement from the following
- Routing
- PERT is applied for
- Discrepancies of bar chart techniques are
A.
If the float is positive and the activity is delayed by a period equal to its total float, the completion of project in not delayed |
B.
If the float of an activity is negative, delay in its performance is bound to delay the completion of project |
C.
If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project |
D.
All of the above |