Home / Mechanical Engineering / Industrial Engineering and Production Management :: Section 2

Mechanical Engineering :: Industrial Engineering and Production Management

  1. Valve analysis is particularly of interest when

  2. A.
    jobbing work economics are involved
    B.
    production is on large scale
    C.
    only few components are involved
    D.
    costly equipment is used

    View Answer

    Workspace

    Discuss Discuss in Forum


  3. The type of layout used for manufacturing steam turbines, is

  4. A.
    product layout
    B.
    process layout
    C.
    fixed position layout
    D.
    any one of these

    View Answer

    Workspace

    Discuss Discuss in Forum


  5. For material transportation, conveyors are used when the prevailing conditions include

  6. A.
    loads are uniform
    B.
    routes do not vary
    C.
    materials move relatively continuously
    D.
    all of these

    View Answer

    Workspace

    Discuss Discuss in Forum


  7. The planning and scheduling of job order manufacturing differ from planning and scheduling of mass production manufacturing.

  8. A.
    Correct
    B.
    Incorrect

    View Answer

    Workspace

    Discuss Discuss in Forum


  9. Gantt chart gives information about

  10. A.
    scheduling and routing
    B.
    sales
    C.
    production schedule
    D.
    machine utilisation

    View Answer

    Workspace

    Discuss Discuss in Forum


  11. Merit rating is the method of determining the

  12. A.
    relative values of a job
    B.
    worker's performance on a job
    C.
    worth of a machine
    D.
    value of overall production

    View Answer

    Workspace

    Discuss Discuss in Forum


  13. PERT stands for

  14. A.
    Programme Estimation and Reporting Technique
    B.
    Process Estimation and Review Technique
    C.
    Programme Evaluation and Review Technique
    D.
    Planning Estimation and Resulting Technique

    View Answer

    Workspace

    Discuss Discuss in Forum


  15. In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker

  16. A.
    whose output exceeds 67% efficiency
    B.
    on the percentage of time saved
    C.
    on the percentage of time worked
    D.
    on the percentage of standard time

    View Answer

    Workspace

    Discuss Discuss in Forum


  17. M.T.M. is used to

  18. A.
    improve existing methods
    B.
    establish time standards
    C.
    develop effective methods in advance of the beginning of production
    D.
    all of the above

    View Answer

    Workspace

    Discuss Discuss in Forum


  19. A dummy activity in a net work diagram

  20. A.
    is represented by a dotted line
    B.
    is an artificial activity
    C.
    does not consume time or resources
    D.
    all of these

    View Answer

    Workspace

    Discuss Discuss in Forum