Civil Engineering :: Estimating and Costing
- Pick up the correct statement from the following:
- Pick up the correct statement from the following:
-
Referring of given figure, pick up the correct statement from the following:
- The height of the sink of wash basin above floor level is kept
- The unit of measurement is per quintal for the following:
- The expected out turn for earth work in excavation in ordinary soil per workman per day is
- The expected out turn of 2.5 cm cement concrete floor per mansion per day
- Cost of fittings and their fixing is specified for the following sanitary fittings
A.
The estimated value of the work excluding the amount for contingencies, work charged establishment, tool and plants, is called work value |
B.
The actual expenditure involved to complete a work including incidental, establishment and travelling charges, is called actual cost |
C.
The formal acceptance by the administrative department for incurring an expenditure on the work, is called administrative approval |
D.
All the above |
A.
The incidental expenses of a miscellaneous character which could not be predicted during preparation of the estimate, is called contingencies |
B.
Additional supervising staff engaged at work site, is called work charged establishment |
C.
Detailed specifications specify qualities, quantities and the proportions of materials to be used for a particular item |
D.
All the above |